After
nearly two years of planning, we began prefabricating our wooden modules in mid-December
of 2021.
The modules will then be transported to our construction site at the
TH Rosenheim, where we will be able to complete our levelup prototype.
Here you can keep track on our construction progress:
28.04.2022
Today the windows of our HDU were delivered. The windows contain recycled vacuum hybrid glass.
The ventilation system was completed. In addition, the grey water tanks are already in place and the heating system is being installed.
27.04.2022
20.04.2022
The steel staircase for the second floor was delivered and assembled.
The HDU will be heated with an electric heat pump. For this purpose, the copper pipes for the floor heating were laid in the living area today.
11.04.2022
After there
was already great progress on the first floor, the elements for the upper floor
arrived today.
Here will be a greenhouse, a technical room and a roof terrace.
28.03.22
The
interior construction is moving forward in big steps.
At the same time we are
already working on the furniture construction in the workshops.
02.03.22
22.02.22
For
insulation, a vapour barrier and wood fiber boards are installed.
In our next steps, we got our construction site ready for rain and snow so that the construction of the HDU could continue without any problems!
After that our team continued to work diligently and achieved a lot of progress.
04.02.2022
We prepared everything for our Topping-out ceremony in the evening.
To make sure that everybody know what's happening on our construction site our corporate design team attached many construction site banners and posters across the building fences.
The party was a great success and a big milestone for the whole team!
24.01.2022
Our modules
arrived at the construction site, which is located directly next to the
Rosenheim Technical University.
Our team leaders had been waiting in great anticipation for the trucks.
Upon arrival, everyone lent a helping hand to get the modules in place.
19.01.2022
15.11.2022
Preparation of the levelup HDU construction area.